Dept. of Trans. PROGRESS Serial No. Contract No. 19-017-16-10 11-414304 PROGRESS PAYMENT VOUCHER %complete: %time: 65% 100% Location: Federal Project: 11-SD-79-34.2/36.5 ACST-P079(42) Progress payment No. 008 Payment period ending: 01-20-19 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 715,713.20 222,041.60 2. a. Extra Work 21,553.54 0.00 b. Adustment Comp. 3. Materials on Hand 0.00 -13,261.44 4. Earned Subject to Retention 737,266.74 208,780.16 5. Mobilization 135,000.00 6,750.00 6. Total Work Completed 872,266.74 7. Deductions -192,000.00 -192,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions -23,911.16 -20,878.02 c. Reduction after 95% Comp. 9. Total pay to Contractor 656,355.58 2,652.14 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,652.14