Dept. of Trans. PROGRESS Serial No. Contract No. 18-355-17-43 11-414404 PROGRESS PAYMENT VOUCHER %complete: %time: 60% 95% Location: Federal Project: 11-SD-94-5.8/9.3 ACNH-P094(65) Progress payment No. 009 Payment period ending: 12-20-18 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,513,502.16 225,216.12 2. a. Extra Work 19,230.41 2,820.51 b. Adustment Comp. 3. Materials on Hand 0.00 -2,209.00 4. Earned Subject to Retention 1,532,732.57 225,827.63 5. Mobilization 80,000.00 0.00 6. Total Work Completed 1,612,732.57 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,612,732.57 225,827.63 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 225,827.63