Dept. of Trans. PROGRESS Serial No. Contract No. 16-264-18-13 11-414904 PROGRESS PAYMENT VOUCHER %complete: %time: 22% 18% Location: Federal Project: 11-SD-67-R21.0/21.6 STP-P067(73) Progress payment No. 004 Payment period ending: 09-20-16 HAZARD CONSTRUCTION COMPANY 6465 MARINDUSTRY DR SAN DIEGO CA 92121 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 526,031.22 115,753.00 2. a. Extra Work 1,439.93 1,439.93 b. Adustment Comp. 159.93 159.93 3. Materials on Hand 24,902.84 -35,209.40 4. Earned Subject to Retention 552,533.92 82,143.46 5. Mobilization 277,500.00 0.00 6. Total Work Completed 805,131.08 7. Deductions -7,651.62 -5,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 822,382.30 77,143.46 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 77,143.46