Dept. of Trans. PROGRESS Serial No. Contract No. 18-234-14-22 11-415304 PROGRESS PAYMENT VOUCHER %complete: %time: 10% 15% Location: Federal Project: 11-SD-163-2.5/4.0 CSTG-P163(30) Progress payment No. 002 Payment period ending: 08-20-18 WESTERN RIM CONSTRUCTORS INC. 621 S ANDREASEN DR #B ESCONDIDO CA 92029 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 376,601.95 106,008.02 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 63,717.96 63,717.96 4. Earned Subject to Retention 440,319.91 169,725.98 5. Mobilization 349,209.00 349,209.00 6. Total Work Completed 725,810.95 7. Deductions -15,897.97 -15,897.97 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 773,630.94 503,037.01 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 503,037.01