Dept. of Trans. PROGRESS Serial No. Contract No. 16-144-14-33 11-415404 PROGRESS PAYMENT VOUCHER %complete: %time: 49% 56% Location: Federal Project: 11-SD-8-16.0/R30.5 HSNH-PIG 008-1(317) Progress payment No. 005 Payment period ending: 05-20-16 HAZARD CONSTRUCTION COMPANY 6465 MARINDUSTRY DR SAN DIEGO CA 92121 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 629,376.06 118,981.06 2. a. Extra Work 2,833.62 0.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 632,209.68 118,981.06 5. Mobilization 137,750.00 0.00 6. Total Work Completed 769,959.68 7. Deductions -6,000.00 -3,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 763,959.68 115,981.06 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 115,981.06