Dept. of Trans. PROGRESS Serial No. Contract No. 16-172-13-05 11-415404 PROGRESS PAYMENT VOUCHER %complete: %time: 56% 75% Location: Federal Project: 11-SD-8-16.0/R30.5 HSNH-PIG 008-1(317) Progress payment No. 006 Payment period ending: 06-20-16 HAZARD CONSTRUCTION COMPANY 6465 MARINDUSTRY DR SAN DIEGO CA 92121 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 737,982.69 108,606.63 2. a. Extra Work 2,833.62 0.00 b. Adustment Comp. 3. Materials on Hand 41,373.99 41,373.99 4. Earned Subject to Retention 782,190.30 149,980.62 5. Mobilization 145,000.00 7,250.00 6. Total Work Completed 885,816.31 7. Deductions -9,000.00 -3,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions -14,998.06 -14,998.06 c. Reduction after 95% Comp. 9. Total pay to Contractor 903,192.24 139,232.56 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 139,232.56