Dept. of Trans. PROGRESS Serial No. Contract No. 17-142-15-54 11-415704 PROGRESS PAYMENT VOUCHER %complete: %time: 19% 37% Location: Federal Project: 11-SD-78-0.0/R16.5 ACHS-NHPP-0(781) Progress payment No. 004 Payment period ending: 05-20-17 FUTURE DB INTERNATIONAL INC 8707 RESEARCH DR IRVINE CA 92618 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 839,686.56 266,990.92 2. a. Extra Work 862.50 0.00 b. Adustment Comp. 3. Materials on Hand 74,361.66 -4,390.50 4. Earned Subject to Retention 914,910.72 262,600.42 5. Mobilization 75,525.00 15,900.00 6. Total Work Completed 916,074.06 7. Deductions -4,000.00 -2,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 986,435.72 276,500.42 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 276,500.42