Dept. of Trans. PROGRESS Serial No. Contract No. 17-234-10-34 11-415704 PROGRESS PAYMENT VOUCHER %complete: %time: 38% 72% Location: Federal Project: 11-SD-78-0.0/R16.5 ACHS-NHPP-0(781) Progress payment No. 007 Payment period ending: 08-20-17 FUTURE DB INTERNATIONAL INC 8707 RESEARCH DR IRVINE CA 92618 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,716,330.70 385,529.46 2. a. Extra Work 101,178.37 6,437.36 b. Adustment Comp. 3. Materials on Hand 73,101.52 23,651.13 4. Earned Subject to Retention 1,890,610.59 415,617.95 5. Mobilization 75,525.00 0.00 6. Total Work Completed 1,893,034.07 7. Deductions -5,000.00 10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,961,135.59 425,617.95 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 425,617.95