Dept. of Trans. PROGRESS Serial No. Contract No. 16-327-17-21 11-416004 PROGRESS PAYMENT VOUCHER %complete: %time: 23% 65% Location: Federal Project: 11-SD-5-0.0/54.8 STP-000C(422) Progress payment No. 003 Payment period ending: 11-20-16 SELECT ELECTRIC INC 2790 BUSINESS PARK DR VISTA CA 92081 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 353,792.28 57,478.75 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 353,792.28 57,478.75 5. Mobilization 138,913.50 0.00 6. Total Work Completed 492,705.78 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 492,705.78 57,478.75 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 57,478.75