Dept. of Trans. PROGRESS Serial No. Contract No. 15-111-14-13 11-416104 PROGRESS PAYMENT VOUCHER %complete: %time: 76% 53% Location: Federal Project: 11-SD-15-M20.3/M20.9 NONE Progress payment No. 006 Payment period ending: 04-20-15 HAZARD CONSTRUCTION COMPANY P O BOX 229000 SAN DIEGO CA 921929000 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 380,879.72 338,882.07 2. a. Extra Work 30,154.28 0.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 411,034.00 338,882.07 5. Mobilization 50,000.00 12,500.00 6. Total Work Completed 461,034.00 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 461,034.00 351,382.07 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 351,382.07