Dept. of Trans. PROGRESS Serial No. Contract No. 14-295-08-46 11-416404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 95% 98% 11-SD-78-R17.0/R17.4 Federal Project: NONE Progress payment No. 03 Payment period ending: 10-20-14 DREAMBUILDER 1324 E LAWSON LN PLACENTIA CA 92870 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 662,293.95 584,386.85 2.a. Extra Work b. Adjustment Comp. -3,035.18 -3,035.18 3. Materials on Hand 4. Earned Subject to Retention 659,258.77 581,351.67 5. Mobilization 35,791.50 8,947.88 6. Total Work Completed 695,050.27 7. Deductions -10,000.00 -10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 685,050.27 580,299.55 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 580,299.55