Dept. of Trans. SEMI-FINAL Serial No. Contract No. 15-048-10-03 11-416404 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 11-SD-78-R17.0/R17.4 NONE Progress payment No. 005 Payment period ending: 11-04-14 DREAMBUILDER 1324 E LAWSON LN PLACENTIA CA 92870 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 677,153.85 6,400.00 2. a. Extra Work 38,519.37 38,519.37 b. Adustment Comp. -3,035.18 0.00 3. Materials on Hand 4. Earned Subject to Retention 712,638.04 44,919.37 5. Mobilization 35,791.50 0.00 6. Total Work Completed 748,429.54 7. Deductions -8,400.00 10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 740,029.54 54,919.37 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 54,919.37