Dept. of Trans. PROGRESS Serial No. Contract No. 19-165-18-16 11-416604 PROGRESS PAYMENT VOUCHER %complete: %time: 38% 38% Location: Federal Project: 11-SD-94-29.4/29.7 HSNH-P094(66) Progress payment No. 004 Payment period ending: 06-20-19 LB CIVIL CONSTRUCTION INC 324 EAST VALLEY PKWY ESCONDIDO CA 92025 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 777,175.02 26,740.02 2. a. Extra Work 29,077.29 6,625.29 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 806,252.31 33,365.31 5. Mobilization 192,850.00 0.00 6. Total Work Completed 999,102.31 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 999,102.31 33,365.31 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 33,365.31