Dept. of Trans. PROGRESS Serial No. Contract No. 17-054-13-06 11-416804 PROGRESS PAYMENT VOUCHER %complete: %time: 23% 7% Location: Federal Project: 11-SD-163-3.7/3.7 ACHS-NHPI 0081-320E Progress payment No. 001 Payment period ending: 02-20-17 WESTERN RIM CONSTRUCTORS INC. 621 S ANDREASEN DR #B ESCONDIDO CA 92029 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 174,141.42 174,141.42 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 174,141.42 174,141.42 5. Mobilization 84,909.00 84,909.00 6. Total Work Completed 259,050.42 7. Deductions -17.65 -17.65 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 259,032.77 259,032.77 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 259,032.77