Dept. of Trans. PROGRESS Serial No. Contract No. 22-053-16-27 11-418104 PROGRESS PAYMENT VOUCHER %complete: %time: 81% 100% Location: Federal Project: 11-SD-5-2.3/R14.0 ACST-X073(142) Progress payment No. 012 Payment period ending: 02-20-22 PAL GENERAL ENGINEERING INC 2364 PASEO DE LAS AMERICAS #1 SAN DIEGO CA 92154 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,071,461.20 335,260.29 2. a. Extra Work 20,459.38 2,617.00 b. Adustment Comp. 3. Materials on Hand 129,245.81 -180,696.19 4. Earned Subject to Retention 2,221,166.39 157,181.10 5. Mobilization 125,000.00 0.00 6. Total Work Completed 2,216,920.58 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions -89,858.73 -15,718.11 c. Reduction after 95% Comp. 9. Total pay to Contractor 2,256,307.66 141,462.99 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 141,462.99