Dept. of Trans. PROGRESS Serial No. Contract No. 18-355-11-27 11-418514 PROGRESS PAYMENT VOUCHER %complete: %time: 62% 60% Location: Federal Project: 11-IMP-8-R40.4/R45.5 ACIM-082(109) Progress payment No. 019 Payment period ending: 12-20-18 SECURITY PAVING COMPANY INC 13170 TELFAIR AVE SYLMAR CA 91342 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 42,748,319.64 447,129.04 2. a. Extra Work 185,731.18 0.00 b. Adustment Comp. 576,037.60 0.00 3. Materials on Hand 4. Earned Subject to Retention 43,510,088.42 447,129.04 5. Mobilization 3,100,000.00 0.00 6. Total Work Completed 46,610,088.42 7. Deductions -21,186.82 515.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 46,588,901.60 447,644.04 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 447,644.04