Dept. of Trans. PROGRESS Serial No. Contract No. 19-324-16-00 11-418514 PROGRESS PAYMENT VOUCHER %complete: %time: 95% 97% Location: Federal Project: 11-IMP-8-R40.4/R45.5 ACIM-082(109) Progress payment No. 030 Payment period ending: 11-20-19 SECURITY PAVING COMPANY INC 3075 TOWNSGATE RD #200 WESTLAKE VILLAGE CA 91361 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 64,439,947.02 174,695.54 2. a. Extra Work 475,610.68 43,313.04 b. Adustment Comp. 706,005.02 -30,460.12 3. Materials on Hand 4. Earned Subject to Retention 65,621,562.72 187,548.46 5. Mobilization 3,100,000.00 0.00 6. Total Work Completed 68,721,562.72 7. Deductions -60,657.82 46,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 68,660,904.90 233,548.46 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 233,548.46