Dept. of Trans. PROGRESS Serial No. Contract No. 18-113-07-41 11-418524 PROGRESS PAYMENT VOUCHER %complete: %time: 92% 39% Location: Federal Project: 11-IMP-8-R83.1/R90.0 ACIM-008-2(110) Progress payment No. 012 Payment period ending: 04-20-18 COFFMAN SPECIALTIES INC 9685 VIA EXCELENCIA #200 SAN DIEGO CA 92126 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 34,063,649.46 1,188,307.93 2. a. Extra Work 436,357.07 64,060.63 b. Adustment Comp. 153,233.79 0.00 3. Materials on Hand 31,352.08 31,352.08 4. Earned Subject to Retention 34,684,592.40 1,283,720.64 5. Mobilization 3,846,500.00 0.00 6. Total Work Completed 38,499,740.32 7. Deductions -44,383.30 -6,285.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 38,486,709.10 1,277,435.64 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,277,435.64