Dept. of Trans. PROGRESS Serial No. Contract No. 18-264-10-41 11-418524 PROGRESS PAYMENT VOUCHER %complete: %time: 98% 58% Location: Federal Project: 11-IMP-8-R83.1/R90.0 ACIM-008-2(110) Progress payment No. 017 Payment period ending: 09-20-18 COFFMAN SPECIALTIES INC 9685 VIA EXCELENCIA #200 SAN DIEGO CA 92126 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 34,865,844.51 81,239.97 2. a. Extra Work 982,951.07 25,997.13 b. Adustment Comp. 156,595.51 0.00 3. Materials on Hand 4. Earned Subject to Retention 36,005,391.09 107,237.10 5. Mobilization 3,846,500.00 0.00 6. Total Work Completed 39,851,891.09 7. Deductions -91,772.21 2,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 39,760,118.88 109,237.10 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 109,237.10