Dept. of Trans. PROGRESS Serial No. Contract No. 19-018-13-37 11-419104 PROGRESS PAYMENT VOUCHER %complete: %time: 59% 65% Location: Federal Project: 11-SD-8-0.0/18.4 ACST-X073(125) Progress payment No. 011 Payment period ending: 01-20-19 FBD VANGUARD CONSTRUCTION INC 550 GREENVILLE RD LIVERMORE CA 94550 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,999,882.28 368,268.13 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 0.00 -191,595.00 4. Earned Subject to Retention 4,999,882.28 176,673.13 5. Mobilization 1,000,000.00 50,000.00 6. Total Work Completed 5,999,882.28 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 5,999,882.28 226,673.13 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 226,673.13