Dept. of Trans. PROGRESS Serial No. Contract No. 21-080-08-48 11-419304 PROGRESS PAYMENT VOUCHER %complete: %time: 10% 15% Location: Federal Project: 11-SD-78-N17.6/R21.3 ACNH-P078(120) Progress payment No. 003 Payment period ending: 03-20-21 HAZARD CONSTRUCTION COMPANY 10529 VINE ST LAKESIDE CA 92040 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 562,164.50 304,156.75 2. a. Extra Work 13,791.72 10,682.12 b. Adustment Comp. 3. Materials on Hand 71,055.86 43,170.16 4. Earned Subject to Retention 647,012.08 358,009.03 5. Mobilization 595,000.00 595,000.00 6. Total Work Completed 1,170,956.22 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,242,012.08 953,009.03 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 953,009.03