Dept. of Trans. PROGRESS Serial No. Contract No. 20-006-08-53 11-419504 PROGRESS PAYMENT VOUCHER %complete: %time: 80% 69% Location: Federal Project: 11-SD-52-3.8/5.1 B1NH-X073(133) Progress payment No. 014 Payment period ending: 12-20-19 HAZARD CONSTRUCTION COMPANY PO BOX 229000 SAN DIEGO CA 921929000 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 8,394,551.11 348,725.11 2. a. Extra Work 71,184.26 5,825.07 b. Adustment Comp. -2,514.58 0.00 3. Materials on Hand 176,768.00 -49,039.00 4. Earned Subject to Retention 8,639,988.79 305,511.18 5. Mobilization 1,100,000.00 0.00 6. Total Work Completed 9,563,220.79 7. Deductions -10,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 9,729,988.79 305,511.18 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 305,511.18