Dept. of Trans. PROGRESS Serial No. Contract No. 19-165-18-19 11-419904 PROGRESS PAYMENT VOUCHER %complete: %time: 50% 30% Location: Federal Project: 11-SD-805-27.1/28.9 B1IM-805-1(638) Progress payment No. 006 Payment period ending: 06-20-19 FLATIRON WEST, INC. 1770 LA COSTA MEADOWS DR SAN MARCOS CA 92078 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,307,609.41 582,501.53 2. a. Extra Work 64,813.98 2,467.14 b. Adustment Comp. 750.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 2,373,173.39 584,968.67 5. Mobilization 475,000.00 0.00 6. Total Work Completed 2,848,173.39 7. Deductions -7,089.75 -7,089.75 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 2,841,083.64 577,878.92 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 577,878.92