Dept. of Trans. PROGRESS Serial No. Contract No. 21-208-09-21 11-420004 PROGRESS PAYMENT VOUCHER %complete: %time: 79% 73% Location: Federal Project: 11-SD-94-10.4/14.9 ACNH-P094(67) Progress payment No. 010 Payment period ending: 07-20-21 GRANITE CONSTRUCTION COMPANY PO BOX 50085 WATSONVILLE CA 95077 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 7,459,275.84 723,791.53 2. a. Extra Work 707,365.47 211,675.13 b. Adustment Comp. 3. Materials on Hand 241,763.00 0.00 4. Earned Subject to Retention 8,408,404.31 935,466.66 5. Mobilization 650,000.00 0.00 6. Total Work Completed 8,816,641.31 7. Deductions -45,400.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 9,013,004.31 935,466.66 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 935,466.66