Dept. of Trans. PROGRESS Serial No. Contract No. 19-200-15-35 11-420104 PROGRESS PAYMENT VOUCHER %complete: %time: 9% 2% Location: Federal Project: 11-SD-5-R25.9/R26.8 ACIM-005-1(641) Progress payment No. 001 Payment period ending: 07-20-19 HAZARD CONSTRUCTION COMPANY 6465 MARINDUSTRY DR SAN DIEGO CA 92121 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 147,792.50 147,792.50 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 147,792.50 147,792.50 5. Mobilization 176,250.00 176,250.00 6. Total Work Completed 324,042.50 7. Deductions -13.55 -13.55 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 324,028.95 324,028.95 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 324,028.95