Dept. of Trans. PROGRESS Serial No. Contract No. 19-353-17-50 11-420304 PROGRESS PAYMENT VOUCHER %complete: %time: 46% 60% Location: Federal Project: 11-SD-52-0.4/14.8 SNHG-P052(20) Progress payment No. 004 Payment period ending: 12-20-19 HAZARD CONSTRUCTION COMPANY 6465 MARINDUSTRY DR SAN DIEGO CA 92121 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 716,900.35 158,314.15 2. a. Extra Work 18,144.53 6,845.09 b. Adustment Comp. 3. Materials on Hand 129,739.74 0.00 4. Earned Subject to Retention 864,784.62 165,159.24 5. Mobilization 180,500.00 0.00 6. Total Work Completed 915,544.88 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,045,284.62 165,159.24 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 165,159.24