Dept. of Trans. PROGRESS Serial No. Contract No. 21-296-12-34 11-420704 PROGRESS PAYMENT VOUCHER %complete: %time: 60% 64% Location: Federal Project: 11-SD-5-0.0/60.0 NONE Progress payment No. 012 Payment period ending: 10-20-21 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,190,334.02 567,464.94 2. a. Extra Work 53,559.23 0.00 b. Adustment Comp. 3. Materials on Hand 111,218.30 -16,923.00 4. Earned Subject to Retention 2,355,111.55 550,541.94 5. Mobilization 150,000.00 7,500.00 6. Total Work Completed 2,393,893.25 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 2,505,111.55 558,041.94 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 558,041.94