Dept. of Trans. PROGRESS Serial No. Contract No. 21-321-19-14 11-420704 PROGRESS PAYMENT VOUCHER %complete: %time: 62% 64% Location: Federal Project: 11-SD-5-0.0/60.0 NONE Progress payment No. 013 Payment period ending: 11-20-21 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,288,376.02 98,042.00 2. a. Extra Work 53,790.07 230.84 b. Adustment Comp. 3. Materials on Hand 107,178.30 -4,040.00 4. Earned Subject to Retention 2,449,344.39 94,232.84 5. Mobilization 150,000.00 0.00 6. Total Work Completed 2,492,166.09 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 2,599,344.39 94,232.84 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 94,232.84