Dept. of Trans. PROGRESS Serial No. Contract No. 22-021-16-03 11-420704 PROGRESS PAYMENT VOUCHER %complete: %time: 78% 64% Location: Federal Project: 11-SD-5-0.0/60.0 NONE Progress payment No. 015 Payment period ending: 01-20-22 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,938,104.19 394,425.17 2. a. Extra Work 53,790.07 0.00 b. Adustment Comp. 3. Materials on Hand 0.00 -107,178.30 4. Earned Subject to Retention 2,991,894.26 287,246.87 5. Mobilization 150,000.00 0.00 6. Total Work Completed 3,141,894.26 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 3,141,894.26 287,246.87 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 287,246.87