Dept. of Trans. PROGRESS Serial No. Contract No. 20-141-18-29 11-420804 PROGRESS PAYMENT VOUCHER %complete: %time: 89% 92% Location: Federal Project: 11-SD-15-8.4/8.4 B1NH-X073(134) Progress payment No. 009 Payment period ending: 05-20-20 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,465,242.95 773,089.75 2. a. Extra Work 65,482.41 22,594.17 b. Adustment Comp. 3. Materials on Hand 306,644.00 -261,166.00 4. Earned Subject to Retention 2,837,369.36 534,517.92 5. Mobilization 91,000.00 0.00 6. Total Work Completed 2,621,725.36 7. Deductions -50,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 2,878,369.36 534,517.92 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 534,517.92