Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 21-022-10-56 11-420804 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 11-SD-15-8.4/8.4 B1NH-X073(134) Progress payment No. 010 Payment period ending: 12-21-20 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,719,827.59 254,584.64 2. a. Extra Work 101,620.39 36,137.98 b. Adustment Comp. 3. Materials on Hand 0.00 -306,644.00 4. Earned Subject to Retention 2,821,447.98 -15,921.38 5. Mobilization 91,000.00 0.00 6. Total Work Completed 2,912,447.98 7. Deductions -322,400.00 -272,400.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 2,590,047.98 -288,321.38 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate -288,321.38