Dept. of Trans. PROGRESS Serial No. Contract No. 18-330-14-41 11-421204 PROGRESS PAYMENT VOUCHER %complete: %time: 34% 30% Location: Federal Project: 11-SD-52-13.3/14.8 SNHG-P052(19) Progress payment No. 002 Payment period ending: 11-20-18 HAZARD CONSTRUCTION COMPANY 6465 MARINDUSTRY DR SAN DIEGO CA 92121 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 263,655.00 97,945.50 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 263,655.00 97,945.50 5. Mobilization 95,000.00 20,000.00 6. Total Work Completed 358,655.00 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 358,655.00 117,945.50 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 117,945.50