Dept. of Trans. PROGRESS Serial No. Contract No. 19-112-14-30 11-421204 PROGRESS PAYMENT VOUCHER %complete: %time: 40% 54% Location: Federal Project: 11-SD-52-13.3/14.8 SNHG-P052(19) Progress payment No. 006 Payment period ending: 04-20-19 HAZARD CONSTRUCTION COMPANY 6465 MARINDUSTRY DR SAN DIEGO CA 92121 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 357,947.40 61,909.10 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 168,341.00 0.00 4. Earned Subject to Retention 526,288.40 61,909.10 5. Mobilization 100,000.00 5,000.00 6. Total Work Completed 457,947.40 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 626,288.40 66,909.10 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 66,909.10