Dept. of Trans. PROGRESS Serial No. Contract No. 24-110-13-37 11-422004 PROGRESS PAYMENT VOUCHER %complete: %time: PEP SAT Location: Federal Project: 11-SD-5-R31.8/R32.2 NONE 11-SD-5-R32.8/R32.8 Progress payment No. 030 Payment period ending: 04-20-24 DIVERSIFIED LANDSCAPE COMPANY 21730 BUNDY CANYON RD WILDOMAR CA 92595 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 442,311.54 1,878.20 2. a. Extra Work 37,303.29 0.00 b. Adustment Comp. 5,512.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 485,126.83 1,878.20 5. Mobilization 39,500.00 0.00 6. Total Work Completed 524,626.83 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 524,626.83 1,878.20 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,878.20