Dept. of Trans. PROGRESS Serial No. Contract No. 24-052-11-39 11-422304 PROGRESS PAYMENT VOUCHER %complete: %time: 56% 35% Location: Federal Project: 11-SD-78-0.3/R16.0 B1NH-P078(121) Progress payment No. 013 Payment period ending: 02-20-24 HAZARD CONSTRUCTION ENGR LLC 10529 VINE ST LAKESIDE CA 92040 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,759,607.67 95,037.50 2. a. Extra Work 566,757.61 81,642.46 b. Adustment Comp. 6,626.00 0.00 3. Materials on Hand 264,370.11 -881.16 4. Earned Subject to Retention 6,597,361.39 175,798.80 5. Mobilization 1,300,000.00 65,000.00 6. Total Work Completed 7,632,991.28 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 7,897,361.39 240,798.80 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 240,798.80