Dept. of Trans. PROGRESS Serial No. Contract No. 24-204-08-26 11-422304 PROGRESS PAYMENT VOUCHER %complete: %time: 82% 51% Location: Federal Project: 11-SD-78-0.3/R16.0 B1NH-P078(121) Progress payment No. 018 Payment period ending: 07-20-24 HAZARD CONSTRUCTION ENGR LLC 10529 VINE ST LAKESIDE CA 92040 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 8,734,389.02 593,158.00 2. a. Extra Work 959,757.43 84,860.00 b. Adustment Comp. -36,444.56 1,553.17 3. Materials on Hand 255,792.32 23,379.58 4. Earned Subject to Retention 9,913,494.21 702,950.75 5. Mobilization 1,300,000.00 0.00 6. Total Work Completed 10,957,701.89 7. Deductions -16,500.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 11,196,994.21 702,950.75 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 702,950.75