Dept. of Trans. PROGRESS Serial No. Contract No. 23-258-20-36 11-423704 PROGRESS PAYMENT VOUCHER %complete: %time: 46% 62% Location: Federal Project: 11-SD-8-R31.8/R41.7 ACIM-008-1(68) Progress payment No. 015 Payment period ending: 09-20-23 GRANITE CONSTRUCTION COMPANY PO BOX 50085 WATSONVILLE CA 95077 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 15,815,195.12 1,497,041.36 2. a. Extra Work 747,299.89 74,416.88 b. Adustment Comp. 40,548.33 0.00 3. Materials on Hand 79,171.00 0.00 4. Earned Subject to Retention 16,682,214.34 1,571,458.24 5. Mobilization 3,405,767.10 0.00 6. Total Work Completed 20,008,810.44 7. Deductions -5,000.00 5,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 20,082,981.44 1,576,458.24 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,576,458.24