Dept. of Trans. PROGRESS Serial No. Contract No. 24-166-11-15 11-423804 PROGRESS PAYMENT VOUCHER %complete: %time: 52% 60% Location: Federal Project: 11-SD-94-R9.8/R10.6 ACNH-X073(151) 11-SD-125-12.9/22.3 Progress payment No. 022 Payment period ending: 06-20-24 GRIFFITH COMPANY 12200 BLOOMFIELD AVE SANTA FE SPRINGS CA 90670 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 12,077,644.50 1,688,462.07 2. a. Extra Work 275,047.87 140,207.78 b. Adustment Comp. 25,893.67 0.00 3. Materials on Hand 118,656.70 30,046.38 4. Earned Subject to Retention 12,497,242.74 1,858,716.23 5. Mobilization 2,470,000.00 0.00 6. Total Work Completed 14,848,586.04 7. Deductions -154,437.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 14,812,805.74 1,858,716.23 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,858,716.23