Dept. of Trans. PROGRESS Serial No. Contract No. 24-292-10-41 11-423804 PROGRESS PAYMENT VOUCHER %complete: %time: 73% 74% Location: Federal Project: 11-SD-94-R9.8/R10.6 ACNH-X073(151) 11-SD-125-12.9/22.3 Progress payment No. 026 Payment period ending: 10-20-24 GRIFFITH COMPANY 12200 BLOOMFIELD AVE SANTA FE SPRINGS CA 90670 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 17,712,006.12 380,672.50 2. a. Extra Work 964,912.53 483,916.53 b. Adustment Comp. 25,893.67 0.00 3. Materials on Hand 93,764.23 -249,910.92 4. Earned Subject to Retention 18,796,576.55 614,678.11 5. Mobilization 2,600,000.00 0.00 6. Total Work Completed 21,302,812.32 7. Deductions -154,437.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 21,242,139.55 614,678.11 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 614,678.11