Dept. of Trans. PROGRESS Serial No. Contract No. 22-231-14-59 11-424704 PROGRESS PAYMENT VOUCHER %complete: %time: 75% 39% Location: Federal Project: 11-SD-5-R13.5/R14.4 SIMG-X073(144) Progress payment No. 010 Payment period ending: 08-20-22 PAL GENERAL ENGINEERING INC 2364 PASEO DE LAS AMERICAS #1 SAN DIEGO CA 92154 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,093,669.14 457,203.15 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 0.00 -26,817.00 4. Earned Subject to Retention 2,093,669.14 430,386.15 5. Mobilization 90,000.00 0.00 6. Total Work Completed 2,183,669.14 7. Deductions -614,400.00 -168,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,569,269.14 262,386.15 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 262,386.15