Dept. of Trans. PROGRESS Serial No. Contract No. 24-257-16-14 11-424804 PROGRESS PAYMENT VOUCHER %complete: %time: 79% 40% Location: Federal Project: 11-SD-54-0.0/6.4 ACNH-P054(9) Progress payment No. 013 Payment period ending: 09-20-24 HAZARD CONSTRUCTION ENGR LLC 10529 VINE ST LAKESIDE CA 92040 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 12,253,048.66 1,857,379.26 2. a. Extra Work 186,980.74 34,456.07 b. Adustment Comp. 3. Materials on Hand 568,443.51 -229,260.89 4. Earned Subject to Retention 13,008,472.91 1,662,574.44 5. Mobilization 1,685,000.00 0.00 6. Total Work Completed 14,125,029.40 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 14,693,472.91 1,662,574.44 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,662,574.44