Dept. of Trans. PROGRESS Serial No. Contract No. 23-355-12-19 11-427104 PROGRESS PAYMENT VOUCHER %complete: %time: 45% 41% Location: Federal Project: 11-SD-8-3.0/8.3 ACIM-008(1) Progress payment No. 004 Payment period ending: 12-20-23 FEC FUTURE CONTRACTORS AND ENGINEERS INC 184 TECHNOLOGY DRIVE #205 IRVINE CA 92618 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,143,716.67 266,564.78 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 0.00 -173,599.20 4. Earned Subject to Retention 1,143,716.67 92,965.58 5. Mobilization 410,400.00 0.00 6. Total Work Completed 1,554,116.67 7. Deductions -28,118.44 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,525,998.23 92,965.58 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 92,965.58