Dept. of Trans. PROGRESS Serial No. Contract No. 21-296-12-41 11-427504 PROGRESS PAYMENT VOUCHER %complete: %time: 3% 5% Location: Federal Project: 11-SD-5-0.2/15.2 B1ST-000C(526) Progress payment No. 003 Payment period ending: 10-20-21 HMS CONSTRUCTION INC 2885 SCOTT ST VISTA CA 92081 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 384,994.05 217,394.02 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 340,947.03 340,947.03 4. Earned Subject to Retention 725,941.08 558,341.05 5. Mobilization 90,120.50 90,120.50 6. Total Work Completed 475,114.55 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 816,061.58 648,461.55 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 648,461.55