Dept. of Trans. PROGRESS Serial No. Contract No. 21-322-08-55 11-427504 PROGRESS PAYMENT VOUCHER %complete: %time: 8% 10% Location: Federal Project: 11-SD-5-0.2/15.2 B1ST-000C(526) Progress payment No. 004 Payment period ending: 11-20-21 HMS CONSTRUCTION INC 2885 SCOTT ST VISTA CA 92081 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,266,383.91 881,389.86 2. a. Extra Work 2,057.67 2,057.67 b. Adustment Comp. 3. Materials on Hand 439,815.98 98,868.95 4. Earned Subject to Retention 1,708,257.56 982,316.48 5. Mobilization 135,180.75 45,060.25 6. Total Work Completed 1,403,622.33 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,843,438.31 1,027,376.73 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,027,376.73