Dept. of Trans. PROGRESS Serial No. Contract No. 23-052-10-08 11-427504 PROGRESS PAYMENT VOUCHER %complete: %time: 90% 73% Location: Federal Project: 11-SD-5-0.2/15.2 B1ST-000C(526) Progress payment No. 019 Payment period ending: 02-20-23 HMS CONSTRUCTION INC 2885 SCOTT ST VISTA CA 92081 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 15,662,543.92 755,047.35 2. a. Extra Work 427,283.03 257,496.86 b. Adustment Comp. 588,858.13 0.00 3. Materials on Hand 390,087.94 -483,984.88 4. Earned Subject to Retention 17,068,773.02 528,559.33 5. Mobilization 180,241.00 0.00 6. Total Work Completed 16,858,926.08 7. Deductions -4,651.82 5,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 17,244,362.20 533,559.33 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 533,559.33