Dept. of Trans. PROGRESS Serial No. Contract No. 22-111-16-32 11-428704 PROGRESS PAYMENT VOUCHER %complete: %time: 55% 74% Location: Federal Project: 11-SD-805-3.4/5.1 ACIM-8051(641) Progress payment No. 005 Payment period ending: 04-20-22 ACCU CONSTRUCTION INC 2098 S GRAND AVE #A SANTA ANA CA 92705 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 623,305.90 204,146.50 2. a. Extra Work 22,879.50 14,584.23 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 646,185.40 218,730.73 5. Mobilization 20,000.00 1,000.00 6. Total Work Completed 666,185.40 7. Deductions -30,402.00 -30,402.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 635,783.40 189,328.73 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 189,328.73