Dept. of Trans. PROGRESS Serial No. Contract No. 24-260-14-50 11-429004 PROGRESS PAYMENT VOUCHER %complete: %time: 40% 33% Location: Federal Project: 11-SD-805-3.5/13.9 ACIM-805(1) Progress payment No. 012 Payment period ending: 09-20-24 SELECT ELECTRIC INC 2790 BUSINESS PARK DR VISTA CA 92081 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,268,207.45 540,381.95 2. a. Extra Work 11,140.68 0.00 b. Adustment Comp. 3. Materials on Hand 639,855.89 417,953.74 4. Earned Subject to Retention 2,919,204.02 958,335.69 5. Mobilization 426,519.60 0.00 6. Total Work Completed 2,705,867.73 7. Deductions -50,000.00 60,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 3,295,723.62 1,018,335.69 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,018,335.69