Dept. of Trans. PROGRESS Serial No. Contract No. 25-108-12-20 11-429004 PROGRESS PAYMENT VOUCHER %complete: %time: 98% 63% Location: Federal Project: 11-SD-805-3.5/13.9 ACIM-805(1) Progress payment No. 019 Payment period ending: 04-20-25 SELECT ELECTRIC INC 1700 E VIA BURTON ANAHEIM CA 92806 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,547,269.09 152,339.76 2. a. Extra Work 619,911.96 28,918.37 b. Adustment Comp. -39,389.00 -39,389.00 3. Materials on Hand 4. Earned Subject to Retention 6,127,792.05 141,869.13 5. Mobilization 448,968.00 0.00 6. Total Work Completed 6,576,760.05 7. Deductions -65,000.00 105,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 6,511,760.05 246,869.13 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 246,869.13