Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 25-205-12-07 11-429004 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 11-SD-805-3.5/13.9 ACIM-805(1) Progress payment No. 022 Payment period ending: 06-25-25 SELECT ELECTRIC INC 1700 E VIA BURTON ANAHEIM CA 92806 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,615,775.34 402.75 2. a. Extra Work 622,035.26 1,133.30 b. Adustment Comp. -39,389.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 6,198,421.60 1,536.05 5. Mobilization 448,968.00 0.00 6. Total Work Completed 6,647,389.60 7. Deductions -10,000.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 6,637,389.60 -8,463.95 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate -8,463.95