Dept. of Trans. PROGRESS Serial No. Contract No. 23-167-18-49 11-429704 PROGRESS PAYMENT VOUCHER %complete: %time: 93% 60% Location: Federal Project: 11-SD-5-R0.3/R72.1 ACST-X073(140) Progress payment No. 020 Payment period ending: 06-20-23 SELECT ELECTRIC INC 2790 BUSINESS PARK DR VISTA CA 92081 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 6,678,817.26 49,614.88 2. a. Extra Work 323,244.06 2,398.34 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 7,002,061.32 52,013.22 5. Mobilization 139,902.00 0.00 6. Total Work Completed 7,141,963.32 7. Deductions -50,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 7,091,963.32 52,013.22 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 52,013.22